Plan bottling line capacity across short contract runs

Build a short-run contract bottling capacity sheet that includes SKU changes, first-piece checks and material reconciliation.

Italiano

Schedule the actual SKU sequence rather than quoting the line’s headline speed. Use accepted output observed for each format and record which intervals belong to preparation, changes and material reconciliation. This lets the contract bottler see how much capacity is already committed.

Worked shift calculation for three short runs

Illustrative schedule in a 480-minute production window
ActivityMinutes bookedOutput or reason
SKU A12040 accepted/min × 120 = 4,800 packs.
SKU B15035 accepted/min × 150 = 5,250 packs.
SKU C9030 accepted/min × 90 = 2,700 packs.
Two format changes4018 and 22 min in the stated directions.
First pieces and material close4025 min checks and 15 min reconciliation.

Apply the remaining time to the real commitment

The illustrative schedule uses 440 minutes and leaves 40. The total is 12,750 accepted packs across three SKUs. Keep the quantities by SKU when assessing commitments. If an additional order needs 30 minutes running and a 20-minute change, the free 40 minutes are insufficient under these assumptions.

Before quoting, verify which checks can run in parallel and whether another client’s pack changes the order. Keep customer-supplied packaging and product approval dates with the schedule.

Read the BottlingScout guide to complete bottling line scope and output

Share the short-run contract bottling schedule with SKU quantities, observed accepted rates and changeover directions.